Skip to main content
erperp-implementationproject-managementtestinggo-live

ERP Implementation Best Practices That Leave Evidence

Nine ERP implementation best practices run as weekly routines, each with the evidence it should leave behind, plus five standard tips worth modifying.

Muhammad Amir

Muhammad Amir

Electrical Engineer & Founder, ECOSIRE (Private) Limited

November 25, 202612 min read2.6k words

The ERP implementation best practices worth keeping are the ones that leave evidence: one real transaction working end to end before any depth, a dated decision log, configuration you can rebuild, a data load you repeat until it is boring, tests re-run every week, real user accounts in every test, named owners for failed integrations, a timed cutover rehearsal, and a first month-end close treated as the final exam. If a practice leaves nothing that another person can open and check, it is an intention. Below are the nine, with the proof to ask for and how each slips.

The rule behind the list: no artefact, no practice

Published lists of best practices tend to agree: get executive support, define goals, clean the data, train the users, test before go-live. Almost none of it is wrong. The trouble is that a project can claim all five while doing none of them. So hold each practice to one question: what could someone open on a Friday afternoon that proves this happened this week? "We are testing" fails. "Here are this week's scripts, who ran them and which ones failed" passes.

This post covers the working rhythm between kickoff and the first closed month. What to agree before that (owner, outcomes, scope, cutover approach) is covered in what to settle before an ERP implementation starts. If those are still open, start there: no weekly routine rescues a project with no owner.

The phase-by-phase sequence, with an exit gate per step, is in the 7 steps of an ERP implementation.

#PracticeWhat you can open on FridayIt has slipped when
1Thin slice firstOne order traced from quotation to reconciled paymentStatus is reported by module
2Decision log with a reopening ruleDated entries, each with a name and a reasonThe same question returns to a third meeting
3Rebuildable configurationA fresh environment built from the written recordOnly one copy of the system is "the right one"
4Repeated data loadA run sheet with counts and totals for the latest loadThe import file is edited by hand after export
5Weekly regression runScript results with names, dates and failuresPassed scripts are never run again
6Real accounts in every testResults logged per role, not per administratorAccess problems appear only after go-live
7Owned integration failuresAn error queue, its age and its ownerThe business notices before the project does
8Timed rehearsalA cutover sheet with actual durations and a last safe momentThe plan has an order but no times
9First close as the final examA closed period, reconciled and signedSupport ends before the month does

1. Push one thin slice through before building anything deep

Make the first build milestone a single ordinary transaction that crosses the whole company: a quotation becomes an order, stock ships, an invoice goes out, a payment is reconciled, and the entries appear in the ledger where the accountant expects them. Plain product, plain customer, ugly documents.

ERP trouble lives at the joins. Sales and Accounting can both look finished while the handover between them is broken, and a module-by-module plan discovers that near the end. A thin slice touches every join while changing the design is still cheap.

How it slips: the slice grows. Discount rules, then freight, then the branded layout, and the first end-to-end run moves back a fortnight. Keep a list called "after the slice" and put everything there.

2. Keep a decision log, and make reopening a decision cost something

Writing decisions down is the easy half. The harder half is the rule for changing one, and it can be short: a settled decision can be reopened by anyone who brings new information, meaning a fact that was not known on the day. A new preference, a new attendee or a louder voice is not new information.

Each entry needs six fields, and a shared spreadsheet is enough:

  • The question, in one sentence
  • The options considered, including "leave it standard"
  • The decision
  • The reason, written so a stranger would follow it
  • Who decided, and the date
  • What new information would justify reopening it

The last field does the most work. It turns a later argument into a lookup.

How it slips: decisions taken in calls and chat never reach the log. Treat anything that is not in the log by the end of the week as undecided, and say so in the status note.

3. Make the configuration rebuildable

If the only complete copy of your configuration is a database somebody has been clicking in for weeks, you cannot prove what is in it. Build a second environment from the project's own record, at least once and well before go-live: an ordered list of settings, modules and versions, import files for master data, custom code from version control. The rebuild exposes the setting nobody wrote down, and gives you a clean place to load data into.

Know what test copies will do to the outside world, too. Odoo's documentation, for example, says that testing databases are neutralised: planned actions, outgoing emails, bank synchronisation, payment providers and delivery methods are among the features switched off. Other systems may leave that to you, and on none of them should a custom integration be assumed to be covered. Before a test copy holds real customer data, check by hand that it cannot email, charge or ship. Ask for the list of differences found while building it, too; an empty one on the first attempt probably means nobody compared.

4. Load the data until it is boring

A trial migration near the end finds the problem when you have least time to fix it. Load early, badly and often, from the same scripts, into an empty environment, until the final load is an event nobody finds interesting. Every load gets the same run sheet:

  1. Date and time of the extract, and who took it
  2. Records out of the old system, records in, records rejected, per object
  3. Control totals: receivables, payables, stock quantity, stock value, trial balance
  4. The difference on each total, and its explanation
  5. Elapsed time for each step

Read the rejected records first. A count that matches because bad rows were skipped on both sides is worse than a mismatch, because it ends the conversation.

How it slips: somebody fixes the export in a spreadsheet to get a load through. The fix is now a manual step that nobody will remember on the night. Corrections belong in the source system or in the script, never in between.

5. Re-run what already passed, every week

Microsoft's implementation guidance makes the point plainly: testing is not a one-time activity at the end of the implementation but a continuous cycle. The version that fits a small company is modest. Keep a short set of scripts covering the flows you cannot trade without. Run all of them every week on the current build. Add one whenever something breaks.

The scripts should say what result is expected before anyone runs them. "Create a credit note and check it looks right" is a tour. "Return two of five units; expect stock up by two, receivable down by two units plus tax, and the original invoice still showing five" is a test.

How it slips: a passed script is treated as finished forever, so the tax change made in week five breaks an invoice that was signed off in week three, and a customer finds it.

6. Never test as administrator

Administrators can do everything, so a flow tested as administrator proves almost nothing about the people who will run it. Ban it from acceptance testing. Create accounts with the exact roles that will exist on day one, and run each script as the role that will perform it.

Test refusals as well as permissions. The person who raises a purchase order should be stopped from approving it, if that is your policy, and the script should record that the system said no.

Ask to see: a short grid of roles against sensitive actions (post a journal entry, change a price, edit bank details, cancel a confirmed order) with allowed or refused in each cell, and the date each was tried.

7. Give every integration a failure owner

Plans describe what an integration does when it works. Ask for the page that covers when it does not: a timeout, a duplicate message, a product that exists on one side only. Design for duplicates from the start. Shopify's developer documentation tells app builders that they might receive the same webhook more than once and that processing should be idempotent, so a repeat changes nothing. Assume the same of any system that retries. For each connection, write down:

  • Which system is the authority for each shared field
  • Where a failed message waits, and how it is retried
  • Who looks at that queue, how often, and who covers when they are away
  • The age at which a stuck message becomes someone's problem today
  • The control total that would reveal a lost message, since a message that never arrived raises no error

8. Rehearse the cutover with a clock and a last safe moment

A cutover plan without durations is a list of hopes. Rehearse it in full, on a copy, with the people who will do it for real, and write down how long each step took. Each step can look reasonable while the sum does not fit the window.

Then mark the last safe moment, the point after which going back costs more than going forward. It normally falls when the first real transaction with the outside world happens in the new system. Before that line the fallback is to reopen the old system. After it, the fallback is a different plan, written separately.

A rollback that relies on a backup nobody has restored is not a rollback. The US cyber-security agency CISA advises organisations to regularly test the availability and integrity of backups in a disaster-recovery scenario. Its context is ransomware; the discipline suits a bad go-live night equally well. Restore the backup somewhere else, count the records, and time it.

9. Treat the first month-end close as the final exam

Go-live day proves people can log in and enter things. The first close proves the entries were right. Stock valuation, tax, accruals and reconciliations all meet there, and errors that stayed invisible for weeks surface together. So plan the support period around the close, not around a round number of days, and sort everything that comes in into three piles:

  • Defect: the system does something other than what was agreed. Fixed by whoever built it.
  • Gap: nobody specified this. Goes to the decision log.
  • Habit: it works as agreed and feels unfamiliar. Needs training, not a change.

An item you cannot sort means the agreement was not written clearly enough.

Five standard tips, done differently

You will hear these often. Each works better in a modified form.

The usual adviceA modified versionWhy
Document all requirements before startingDocument the first slice fully and the rest as questions with ownersPeople describe their old system until they have seen the new one move
Secure executive sponsorshipAgree how fast the sponsor answers, in working days, and log it when they do notSupport that takes three weeks to reach is a delay with a title
Avoid all customisationAllow it, with an owner, a test and a removal condition for each itemA blanket ban pushes logic into spreadsheets, where nobody tests it
Run old and new systems in parallelRun one period's figures through both, on a copy, before go-liveDaily double entry tires the people you most need to be careful
Train everyone just before launchLet key users write and run the test scripts, then teach their own teamsWriting the expected result teaches more than watching a session

None of these suits every company. A regulated business may need the full requirements document, and some finance teams will rightly insist on a live parallel period.

The Friday half-hour

Run the first table from top to bottom once a week and count only the rows answered by opening something. Early on, several will be "not yet", and that is fine. Then ask two more questions: what went end to end this week that did not last week, and what is the oldest item nobody owns? Act on any answer that gets vaguer from one week to the next, such as a rehearsal date that has become "soon".

Scaling this down

A small company does not need nine ceremonies. If only three are kept, keep the thin slice, the repeated load and the timed rehearsal, because what they catch is slow and expensive to unwind later. The rest fits in a shared spreadsheet and that half-hour on Friday.

For that scope, a short engagement can be enough. The Odoo implementation sprint runs four weeks from discovery to go-live with two weeks of support afterwards, and is meant for businesses of up to about 50 users on standard apps. If your first close falls outside that window, ask for cover through it before you start. For manufacturing, several companies or many integrations, plan for longer and keep all nine.

Frequently Asked Questions

What are the most important ERP implementation best practices?

Prove one transaction end to end early, log decisions with a rule for reopening them, repeat the data load with control totals, re-run passed tests every week, and rehearse the cutover against a clock. Judge each by the evidence it leaves.

How do you know if an ERP implementation is on track?

Ask for evidence instead of status colours. A project on track can show which flows work end to end, the latest load with its differences explained, this week's test results by role, and a rehearsed cutover that fits its window. Answers that become vaguer from week to week are the earliest reliable warning.

How many trial data migrations should you run?

Enough that the last one is uneventful: the same scripts, no hand edits, every control total explained, and an elapsed time that fits the cutover window. That exit test is more useful than a fixed number.

When is an ERP implementation actually finished?

It is finished when the first period closes cleanly: accounts reconciled, stock valuation agreed, taxes checked and open support items sorted into defects, gaps and habits with owners. Go-live is a milestone on the way there.


Want a second pair of eyes on your project plan, or a small scope to start with? See the Odoo implementation sprint or get in touch.

Tags:erperp-implementationproject-managementtestinggo-live
Share:
Muhammad Amir

Written by

Muhammad Amir

Electrical Engineer and founder of ECOSIRE (Private) Limited. Began his career on JF-17 fighter jet avionics; now ships ERP, AI, and ad-tech systems — including 215+ Odoo modules, an autonomous SEO platform, and AI agent fleets.

Need consulting help?

I offer productized consulting services for ERP, integrations, and AI.

View Services
Chat on WhatsApp